Showing posts with label stormwater. Show all posts

Reduce, Reuse, Recycle: That’s the WSDOT way!

By guest blogger Chelsey Funis from Flatiron Construction

The I-405 Bellevue to Lynnwood project reuses soil moved
from other parts of the project area to build retaining walls,
shown above, and sections of new roadway.
Most of us follow that old mantra of Reduce, Reuse, Recycle without a second thought everyday, whether we’re recycling our used aluminum cans or bringing our reusable grocery bags to the grocery store. But did you know that crews building the latest batch of I-405 improvements are also following that mantra? 

As part of the I-405 NE 6th Street to I-5 Widening and Express Toll Lanes Project, our crews and contractor, Flatiron Constructors, are using a number of sustainable practices to build a better project for our environment and taxpayers. In this case, going green also helps us save a little green. And who doesn’t like that?

So what are we doing to reduce our carbon footprint?

To reduce impacts on nearby aquatic resources, project crews
have built three mitigation sites. Improvements completed this
October in Kirkland, shown above, include new trees,
plantings, rocks and drainage pipes.
Recycling soil and fill material excavated from the 17-mile project site
Major construction projects typically truck in thousands of cubic yards of soil, crushed rock and other organic materials from off-site locations. Using a little creativity, we were able to design the I-405 project and schedule the construction in a way that recycles tested and approved soil and earthen fill material directly from the project site. We then use the recycled soil and fill material in other places on the job. For example, we’re building two retaining walls and a noise berm in Kirkland by reusing earthen material dug up from the footprint of a new northbound I-405 on-ramp in Bothell and other locations throughout the project area.

By reusing soil on site instead of disposing it off-site and buying new material, our crews:
  • Cut back on heavy trucking at longer distances.
  • Save fuel and decrease carbon emissions.
  • Prevent damage to our roads.
  • Reduce the cost and space used at off-site disposal locations.
Because we’re recycling and reusing soil and fill materials, we’ve also eliminated about 300,000 cubic yards of excavation. To put things into perspective, that’s enough soil to build a pile nearly 136 feet tall onto a football field – or nearly two-thirds of the way up to CenturyLink Field’s roof, which rises about 200 feet above the ground. In addition, our commitment to reusing 100 percent of the remaining excess material on site will result in a 2,100-ton reduction of greenhouse gas emissions over the life of the project. That’s the equivalent of a little more than 4,000 cars’ annual greenhouse gas emissions.

Recycling demolished concrete structures
We’re removing  many concrete structures, such as roadway barriers, so that they can be updated to current standards. For this project, crews haul all of this rubble to local recycling facilities that process and repurpose the steel and concrete for other local projects.

Recycling old asphalt pavement
We’re also removing existing asphalt pavement that is past its service life. Crews are grinding and breaking the removed asphalt to build temporary access roads and embankments, as well as reprocessing it back into new asphalt for this and other local projects.

Installing bioswales: smarter drainage ditches
Urban stormwater – the rain and snow melt that runs off surfaces like rooftops, sidewalks, paved streets, highways and parking lots – is one of the biggest environmental threats to the Puget Sound region. Left untreated, stormwater runoff can carry pollutants like oil, fertilizers and pesticides into our waterways, harming creeks, streams and rivers that provide important habitat for fish and wildlife.

Cleaning pollutants from this water and reducing the rate of runoff is a critical component to the Bellevue to Lynnwood project in order to help protect the many nearby wetlands.

To clean pollutants and control the rate of runoff, this project will construct:
  • Eight new or enlarged standard treatment and detention ponds.
  • 3,550 linear feet  (more than half a mile) of biofiltration swales, also known as bioswales, which help capture and treat stormwater by filtering the water through vegetated channels comprised of organic materials like grass and shrubs. 
  • 11,200 linear feet, or more than two miles, of new media filter drains, which we construct along the highway shoulder area. The media filter drains consist of a no-vegetation zone, a grass strip and a mix of native vegetation. These pollutant filters are great for where there is limited space.
Want more information?

What we know now...and didn’t know then – an evolution of environmental awareness

 By guest blogger Ann Briggs

Kelsey Creek, I-405 wetland, 2008
Recent talk about budgets and the effect environmental regulations have on transportation costs have people asking why we spend money on environmental studies, wetlands and things of that sort.

It has me thinking about my own views on the environment and how they have evolved. As a child of the 60s, I remember riding in my parents' car, tossing candy wrappers out the window (sigh!) and my dad dumping the car ashtray on the ground, scattering butts everywhere. We just didn’t give much thought back then about where this stuff ends up…as if it would simply disappear into the wind. We certainly know better now.

Thanks to better science and practices, an environmental awareness and evolution has taken place over the years in the world of transportation too. Much of what we do today to protect the environment and mitigate for the impacts of highway construction is based on lessons learned and a greater understanding of the effects the transportation system has on our surroundings. A significant amount of money is spent fixing the problems that were created in decades past.
Gold Creek side channel I-90, 2009

Environmental missteps, like those tossed candy wrappers, can pile up if we keep repeating them. We used to build roadways with drainage systems that funneled highway runoff directly into lakes and streams. Wetlands were soggy ponds that got in the way of progress, so we drained them. We built culverts to let the water through, but didn’t think about how fish would manage. We built highways in places that made good engineering sense, but not necessarily good community sense.

We now build highways with stormwater management systems to filter out oil and fluids from drippy cars before it enters our streams. We know now that wetlands are critical for reducing flooding, recharging groundwater supplies and providing habitat. Between 1988 and now, we’ve built and monitored 194 wetlands covering 942 acres. Since 1991, we’ve been replacing culverts that block fish and have restored fish passage to more than 900 miles of habitat. We conduct environmental studies to determine how our work will affect communities, cultures, habitats, air, water and noise, and find ways to avoid or mitigate for those impacts. And, we work hard to report the results of those studies in easy-to-read-and-understand formats.

SR 167 Panther Creek fish passage
culvert installation, 2012
While it’s true that none of this work comes cheap, we have to ask ourselves, “Can we really afford the ultimate price of not doing it?” I think not. We’ve made good strides in environmental stewardship, but we’re far from done and we’ll continue to work to create a transportation system that is compatible with communities and nature. We all have a responsibility to future generations to take care of the things that make the Pacific Northwest such a rich and vibrant place to live. It’s the right thing to do.

As we celebrate Earth Day on April 22, think about what you know now that you didn’t know then. What changes have you made as a result of your own environmental evolution?