Seismic retrofit program prepares bridges, overpasses for quakes

By guest blogger Tom Pearce

Steel column jackets, like these used in the seismic retrofit
of the SR 509 Puyallup River Bridge, will be installed
at 12 locations along I-5.
We’re going to have another major earthquake here. OK, I can’t tell you when or where it will be centered, but if you’ve lived around here for a few years, you know we live in a seismically active area.

When the big one hits, transportation infrastructure is going to be critical to the region’s recovery. We’re going to need the freeways and bridges, particularly from Joint Base Lewis-McChord to Seattle, to move supplies and materials to recover and rebuild. To prepare for this, in 1991 we started a seismic retrofit program to minimize and avoid catastrophic bridge failures.

As part of that program, we’re upgrading overpasses along I-5, from SR 18 to South 288th Street in Federal Way, and from Kent’s Military Road to South Rose Street in Seattle. We’re also just wrapping up a project at the M Street and I-705 overpasses in Tacoma. We’re going to strengthen freeway overpasses to help them better withstand earthquakes. How are we going to do this? Well, we’ll add:
  • Steel column jackets: These are steel plates wrapped around the columns that hold up overpasses and bridges to keep them from crumbling and collapsing in an earthquake.

  • Bolster supports: These widen the pier caps that hold up the girders supporting the roadway, making it harder for the girders to slip off in an earthquake.

  • Girder stops: These keep the girders from sliding side-to-side in an earthquake.


We’ll be working at 12 sites between Federal Way and Seattle, strengthening a total of 22 overpasses.  This work is important, but you’re going to see some impacts around worksites. Sidewalk, shoulder and single lane closures are necessary along the roads under I-5 where our contractors will be working.

Most of the work will be done at night, which could be noisy for nearby homes at a few of the locations. We have noise rules and work with each local jurisdiction to do everything we can to limit and mitigate the noise, but in some cases it will still be there. Our contractors will send flyers to homes that could be most affected before starting the work.

Major highways aren’t the only place we’re doing seismic retrofits. We’re also working on the Scatter Creek Bridge, east of Enumclaw. Every winter SR 410 closes at Crystal Mountain Boulevard. The Scatter Creek Bridge is important because it’s the only year-round westerly link for local residents, visitors and emergency vehicles.

Since the program began, we’ve completely retrofitted more than 280 bridges and done partial retrofits on more than 130 others. Even with this year’s work, we’ll still have more than 450 to go.

It takes time, and we’re doing the work as quickly as possible. But as sure as we’re going to have another earthquake, we’ll keep working to strengthen our bridges and overpasses.

Epic Legonians shake things up in Vancouver

By Abbi Russell

A model of the EQ-EAST –
Earth Quake Early Alert System for Transportation
The shaking started with little warning, prompting a flurry of flashing lights just before the suspension bridge started to sway. Thankfully, no one was on the bridge during the earthquake, because, well, it’s made of LEGOs. But had it been a real bridge with traffic, lives could have been saved by EQ-EAST – the Earth Quake Early Alert System for Transportation.

EQ-EAST is the brainchild of a group of aspiring engineers who call themselves the Epic Legonians. The team of fifth graders created the system to warn drivers in advance of an earthquake and prevent them from driving onto bridges as the seismic waves hit.

The system measures seismic movement using sensors installed in buildings and other structures. The sensors trigger a warning system of flashing lights on bridges within the quake zone. The system also has potential for use in homes and businesses to warn people to take cover before the shaking in their area begins.

On Jan. 2, the Legonians presented their research and concept to a panel of nine WSDOT engineering and maintenance staff from Southwest Region and Headquarters. The team, which is part of the For Inspiration and Recognition of Science and Technology (FIRST) LEGO League, was looking for feedback and suggestions as they continue developing their design in advance of a statewide competition in late January. They had also presented to and received feedback from the Arizona, Florida and Oregon departments of transportation.


The Epic Legonians (from left to right: Ramya,
Shruthi, Aishwarya and Zoe) pose with WSDOT staff
The panel was impressed with the team’s research and thoroughness. They asked questions and provided real-world, technical feedback on the system’s potential, how to make it more effective, and other issues to consider in the realm of traffic and transportation.

Southwest Region Bridge Supervisor Mike London feels the concept has a lot of potential. He peppered the team with questions and feedback from the maintenance perspective, and said he’d keep an eye out for further developments.

Keeping people safe and moving is the cornerstone of our work. We are pleased to have had the chance to help the Epic Legonians stretch their minds and develop creative solutions to improve our society.


Seismic bridge retrofitting: And you didn’t even know it!

Winter is barely halfway over, but here at WSDOT we’re quickly transitioning into construction season. If you’re familiar with WSDOT projects, you know what that means: you’ll see the signature orange of our traffic cones, construction barrels, and safety vests as crews get to work improving our state highways.

What you might not know is that our construction activities aren’t limited solely to large, visible projects. Some of our projects are barely noticeable to freeway drivers, and you may not have realized that we’ve been working under your feet (er, car) all along. In fact, if you’ve traveled on I-5 from Seattle to Everett lately, you’ve driven right over one of our active construction sites. Since October 2008, crews have been working to retrofit 19 bridges (overpasses and underpasses) on I-5 between Tukwila and Lynnwood, and are currently working in both Tukwila and Mountlake Terrace.

In plain English, seismic retrofitting means improving a bridge to protect it against future earthquakes. Although these bridges are all structurally safe for everyday traffic, simple upgrades can go a long way towards keeping the bridge intact and motorists safe in the event of a large earthquake.

So how has this work progressed without you noticing all those orange barrels and construction equipment? The trick is that construction occurs beneath the surface of the roadway, focusing on bridge columns, crossbeams and girders.



Improvements to an individual bridge typically include one or more of the following:

  1. Column jacketing – installing a metal jacket around the bridge column. If a concrete column were to crack during an earthquake, the metal jacket would hold the pieces together, preventing the column from crumbling.
  2. Bolster retrofitting – extending the crossbeam to prevent girders from slipping off sideways during an earthquake. Girders support the roadway, so it’s important to keep girders intact.
  3. Girder stops – installing concrete blocks on either side of the girder to stop the girder from sliding or tipping over.



In addition to the 19 bridges that are slated for improvement as part of the I-5 project, there are more than 900 bridges across the state that will be improved as part of the Seismic Retrofit Program. For more information, take a look at the project Web site or the statewide Seismic Retrofit page.

Editor's note: post written by Aurora Jones.