Washington’s newest mega project: Fish barrier corrections
Posted by Unknown in culvert, culvert replacement, culverts, fish barrier corrections, fish passage, fish-friendly on Wednesday, September 17, 2014
By Ann Briggs
You've probably heard about our four “mega projects:” Alaskan Way Viaduct, State Route 520 Bridge, Interstate 405 Corridor and the North Spokane Corridor, but did you hear about the newest one? It's called “Fish Passage” and it's currently unfunded.
Statewide, there are about 6,500 culverts on the state highway system. Of those, about 3,200 are in fish-bearing streams. We're required by law to maintain culverts, fish ways and bridges so that fish have unrestricted passage to upstream and downstream habitat.
![]() |
| SR 530 Moose Creek culvert before correction. |
The amount available for this work in the current biennium is $36 million. Right now we estimate approximately $300 million is needed each two-year budget cycle through 2029-31. The initial estimated cost to comply with the injunction is $2.4 billion at the low end, and likely to go up. As we do more detailed design work on a first round of 34 projects, we are finding that costs are higher than initial estimates for those projects. That's mostly due to limited site-specific information when the initial cost estimates were developed. We anticipate cost estimates for the entire program will stabilize as we learn more about individual site characteristics.
We've been working to improve access to habitat for fish since the 1990s. About 280 fish-barrier correction projects have opened access to more than 975 miles of potential fish habitat.
![]() |
| SR 530 Moose Creek culvert after correction. |
Why do we do this? It's part of our agency's goals to protect natural habitat and water quality. It also supports the Governor's goals for the environment and salmon recovery.
So how did we get here? You have to remember that much of our state's infrastructure was built decades ago. Many of these culverts were installed simply for the purpose of conveying water, before we had the science and understanding of the needs of fish.
In some areas, like Interstate 90 at Snoqualmie Pass, projects that improve fish passage have improved conditions for other species, allowing deer, bear and other wildlife to cross safely under or over the busy freeway lanes – that's safer for drivers too!
Visit our Fish Passage project website for an interactive map of all barrier locations and project details.
Fixing US 2 near Monroe in August so we’re ready for November
Posted by Unknown in culvert replacement, culverts, flooding, rain, US 2 on Friday, November 16, 2012
by guest blogger Bronlea Mishler
Rainy weekend forecast puts fix to the test
“When we inspected the culverts last summer, they really looked like Swiss cheese – holes everywhere,” said John Tellesbo, WSDOT’s Area 3 assistant maintenance superintendent. “We’d patched a few minor sinkholes on the shoulder, but it was just a matter of time before we got a big one that could have caused a serious problem.”
Snow. Ice. Mud. Rivers of rain. When winter weather flings its worst at the northwest, it’s not just drivers that have to bear the brunt of the unpleasantness. The roads themselves take a constant beating from the elements – and that means our maintenance crews have to be on their toes to keep the highways drivable.
Crews use the dry summer months to inspect and repair the highways – everything from filling cracks and patching potholes to replacing signs and maintaining culverts. Getting all that work done in the good weather means that the highways are prepared and ready to meet the bad weather – and that’s good news if you plan to hit the road during the winter months.
While all maintenance is important, our crews give special attention to highway drainage culverts. If you’re like most drivers, you’ve probably never noticed our culverts – that is, unless something has gone wrong. Flooding, potholes, sinkholes and big dips in the road are all highway maladies that can result from clogged or damaged culverts.
Despite our best intentions – and attention – sometimes old culverts don’t make it through a winter unscathed. There’s not much maintenance crews can do in the winter when the corroded old pipes begin to fail, except patch the resulting potholes and road divots. Until recently, the stretch of US 2 near Bickford Avenue was a particular headache for maintenance crews. Five culverts cross beneath the highway, carrying stormwater to nearby detention and treatment areas. And all five of those culverts were one storm away from falling apart.
![]() |
| New piping in place under US 2 |
“We’re very fortunate we fixed them when we did,” Tellesbo said. “This is one less area we have to worry about this winter – and that means our crews can be out cleaning drains and catchbasins and keeping the highways safe.”
Round-the-clock closures on US 2 this weekend to replace “Swiss cheese” culverts
Posted by Unknown in culvert replacement, culverts, US 2 on Friday, August 3, 2012
By guest blogger
Erica Taylor
![]() |
| Crew perform prep work for culvert removal and installation underneath US 2. |